Roads updates:
FACTS:
- Southside subdivision drainage program:
- Due to weather and timeline constraints this project was scheduled to be completed and chip seal ready this summer. Work to be completed prior to chipseal:
- Transitions
- Driveways
- Road regrading
This work will commence on Tulita Street Monday, May 29, 2023. We will inform impacted residents on Thursday, May 25th, 2023.
- Chipseal:
- Contractor assures us that materials and equipment will be brought to Norman Wells on the first barge of the season and the project will commence soon after
- DOT will be regraded prior to the first chipseal application.
- A second street sweeping will occur before chipseal application on already chipsealed roads.
- Driveways on MacKenzie Drive will be crowned or swaled for proper drainage prior to chipseal application.
- Ongoing road maintenance will occur as weather permits.
Please feel free to reach out to the Public Works Manager at 1-867-688-0682 or email at publicworksmanager@normanwells.com