Capital Projects Update

South Subdivision Drainage Project:


Work commenced on Woodland Drive on May 30, 2022.
Project duration is anticipated to be 8 wks.

Forestry Road Ditching Project:


Drainage ditching is now complete. Culvert installation is anticipated to be complete during the first week of July 2022


Chip Seal Road Upgrade:


Chip Seal project is anticipated to start this coming July/August. The project is anticipated to take two weeks!


Landfill Expansion and Slope Stabilization:


Tender was distributed May 20, 2022.
Contractor Site Walk June 2, 2022
Tender Close date June 24, 2022
Anticipated Phase 1 start date: July / Aug 2022: 90 days
Anticipated Phase 2 start date: Spring / Summer 2023: 80 days


Municipal Pool:


Upgrades to the Penguin Palace are anticipate to wrap up by mid July.